    CARTAGENA LNG TANKS

    This project involved building two liquefied natural gas (LNG) storage tanks with a storage capacity of 150,000 m³ each, to later supply the oil pipeline system or load onto petrol tankers. The second tank is currently under construction.

    This project also involved building the foundations and structures necessary for plant processes. The facilities needed included everything from urbanisation to drainage systems for contaminated water treatment.

    ACCIONA also built an electrical substation, security office, and fire station.

    GENERAL INFORMATION

    Location
    Murcia, Spain
    Contract type
    Construction
    Year construction ended
    2009

    Image Gallery

    discover other flagship projects

    ADRIATIC LNG TERMINAL

    Veneto, Italy

    First offshore liquefied natural gas (LNG) terminal in the world.

    GBS-LNG STORAGE

    Madrid, Spain

    GBS infrastructure with storage capacity, bunkering, and medium-scale LNG process.

    Move up